PORTLAND, Maine (AP) Central Maine Power says it has found faster and less costly solutions for large solar projects to connect to the power grid. CMP sent a letter to the Public Utilities Commission on Tuesday, a day after Democratic Gov. Janet Mills called for an investigation.

In the letter, CMP says it’s notifying solar farm developers of its “revised approach.”

The state’s largest electric utility warned developers of 18 projects that it had underestimated the cost of infrastructure upgrades needed to connect to the grid.

Company officials now say “lower-cost upgrades or the complete elimination of upgrades” may be possible.

Latest Headlines

1 hour ago in Local

Republican Jonathon Bush Enters Maine Governor’s Race

Fresh

Bush is the cousin of former President George W. Bush

2 hours ago in Local

Maine Man Arrest for Reportedly Driving 152 mph in New Hampshire

Bryce Legere was booked into the Carroll County Department

3 hours ago in Local

Sen. King to continue to vote for GOP stopgap bill to end shutdown

Maine U.S. Sen. Angus King says he'll continue supporting a stopgap measure proposed by Republicans to open the government.

3 hours ago in Local

11 dogs, 4 cats killed in fire that destroyed Avon home

11 dogs and four cats were killed in a fire in Franklin County.

11 hours ago in Local

Dion Frustrated Over Delay in Renewal of Popular Music Festival

City Council members are clashing over the terms of the contract