Maine Supreme Court upholds lease for $1B power line project

Maine Supreme Court upholds lease for $1B power line project

Photo: clipart.com


PORTLAND, Maine (AP) Maine’s highest court on Tuesday upheld the lease for a small section of state land for a $1 billion electric transmission corridor, a victory for developers who hope to complete the project.

The Supreme Judicial Court ruled unanimously that the Maine Bureau of Parks and Lands acted within its authority in leasing a 1-mile (1.6-kilometer) stretch of the 145-mile (233-kilometer) power transmission line. All told, the state lease covered about 32 acres (13 hectares) of land in western Maine.

The New England Clean Energy Connect remains on hold pending the outcome of another legal case focusing on the constitutionality of a referendum in which Maine voters rebuked the project.

Central Maine Power’s parent company, Avangrid, and Canada’s Hydro Quebec teamed up on the project that would supply up to 1,200 megawatts of Canadian hydropower to the New England power grid.

Supporters say such bold projects are needed to address climate change. Critics contend the power line would destroy woodlands while failing to deliver on promised environmental benefits.

“Today’s ruling by the law court is yet another step in the right direction for Maine’s renewable energy future. The serious need for the NECEC project to reduce our reliance on fossil fuels, combat climate change, and lower energy prices remains unchanged,” said Scott Mahoney, Avangrid’s general counsel.

But opponents decried the court’s conclusion that the lease didn’t represent a substantial alteration or reduction of land warranting a vote of state lawmakers, as required under a 1993 amendment to the Maine Constitution.

State Sen. Rick Bennett, R-Oxford, accused the court of undermining the will of the people who amended the Constitution to protect public lands. “The job of the Supreme Court is to serve the people of Maine and to protect our Constitution,” he said in a statement. “With this ruling, they have instead sucker-punched the people of Maine and subverted our Constitution.”

Most of transmission line would be built along existing utility corridors, but a new 53-mile (85-kilometer) section was needed to reach the Canadian border.

Workers had been clearing trees and setting poles for months when the governor asked for work to be suspended after the referendum last year. The referendum on the project was the costliest in Maine history, topping $90 million and underscoring deep divisions.

The project would be funded by Massachusetts ratepayers, but supporters say the introduction of so much electricity to the grid would stabilize or reduce electricity rates for all consumers. The project would supply enough electricity for about 1 million homes.

Latest Headlines

2 hours ago in Local

An Accused Drunk Driver Arrested for Driving the Wrong Way on I-295

Fresh

The driver was charged with an OUI and Reckless Conduct with a Dangerous Weapon.

1 day ago in Trending, World

King Charles III strips Prince Andrew of titles and evicts him from royal residence

King Charles III on Thursday stripped his disgraced brother Prince Andrew of his remaining titles and evicted him from his royal residence after weeks of pressure to act over his relationship with sex offender Jeffrey Epstein, Buckingham Palace said.

2 days ago in Local

Lobster Population Drops in New England, Overfishing Declared

A regulatory agency says lobster stock has declined by 34% since 2018

2 days ago in Local

Maine Network Ends Primary Care After Medicaid Cut from Trump Admin.

Maine Family Planning operates 18 clinics in the state

2 days ago in Local

Brunswick Police: Woman Rammed Cruiser, Led High Speed Chases Before Arrest

The suspect was denied bail because of underlying bail conditions.